Project | LAU Underground Parking Phase II |
Client | Lebanese American University |
Architect / Consultant | ACE – Associated Consulting Engineers |
Project Duration | 240 days |
Description of Project | An underground parking consisting of 5 basements serving as car parking and technical floors, a ground floor, the roof upper top and the main entrances. La Constructa has undertaken, as the main contractor, the construction phase II of the building including all finishing, electro-mechanical and external works related to this part of the university campus. Approximate built up area of 25000 m². |
Project | Saint-Charles Hospital – Phase 1: Parking |
Client | Congregation des Soeurs des Saints-Coeurs |
Architect / Consultant | Madkour Architects |
Project Duration | 430 days |
Description of Project | The project consists of 3 underground parking floors that could accommodate 230 cars. La Constructa has undertaken, as the main contractor, the execution of all concrete and electro-mechanical works. La Constructa is currently operating this facility for a period of 15 years before transferring it to the Owner. Approximate built up area of 6900 m². |